- Delivery
- Q2 2027
Project Diana is under construction at Heesen’s Oss shipyard. The current official programme schedules delivery for Q2 2027.
New-build intelligence
Track recorded superyacht project stages, verified construction milestones, delivery guidance, builder pipelines and the freshness of each project update.
Project Diana is under construction at Heesen’s Oss shipyard. The current official programme schedules delivery for Q2 2027.
Design, naval architecture and tank testing are complete. Keel laying is scheduled for November 2026, with launch and delivery anticipated in 2030.
Launched by Heesen on 14 March 2026. Later sea-trial and delivery milestones will be added when their exact dates are verified.
The hull and superstructure have been joined. Technical systems and bespoke interior outfitting are under way, with delivery scheduled for Q3 2027.
Project Angelica is under construction. Heesen’s January 2026 programme schedules launch for October 2026, with delivery scheduled for Q2 2027.
The hull and superstructure have been joined and the yacht entered outfitting. Heesen’s January 2026 programme scheduled an April 2026 launch, but no later official launch confirmation has been applied. Delivery remains scheduled for 2026.
The steel hull and aluminium superstructure have been joined at Heesen’s Oss shipyard. Delivery is scheduled for Q1 2028.