Project Timeline & Delivery Intelligence

Track recorded superyacht project stages, verified construction milestones, delivery guidance, builder pipelines and the freshness of each project update.

No invented progress percentages or delivery dates. A project's recorded status shows its current Superyacht Guide project stage. Earlier stages are not automatically treated as independently verified milestones unless a dated milestone is recorded. Expected dates and delivery guidance are shown only where recorded.
Public projects
44
Active pipeline
35
Delivered records
9
Updated ≤90 days
29
With source evidence
44
With dated milestones
20
Delivery-data coverage: 36 public project records currently contain recorded launch or delivery guidance. 0 contain a structured expected launch or delivery date. Free-text guidance such as a year or season is shown as guidance only and is not converted into an invented exact date.
Project pipeline is not build-slot availability. The separate Build Slot & Delivery Tracker currently has no public evidence record proving a specific available slot or hull. Open Build Slot & Delivery Tracker
Clear

Project pipeline

2 matching project records
Hull and superstructure joined

Royal Huisman Project 412

Royal Huisman · 81.00 m
Project: Project 412
Hull: 412
Verified 91–180 days ago
Recorded current project stage
Hull and superstructure joined
Workflow reference: Announced → Construction started → Hull joined → Outfitting → Launched → Sea trials → Delivered. Only dated milestones listed below are independently recorded as milestone events.
Recorded dated milestones
  • 31 March 2026 — Hull and superstructure joined
Delivery
2028
Latest recorded progress

The main hull of Project 412 has been turned upright and its bow section joined. Integration, outfitting and finishing are now progressing toward 2028 delivery.

Latest verified update
31 March 2026
Dated milestones
1
Source records
2
Record verification: Source-backed · Data confidence: High
Outfitting

Royal Huisman Project 410

Royal Huisman · 85.00 m
Project: Project 410
Hull: 410
Review update
Recorded current project stage
Outfitting
Workflow reference: Announced → Construction started → Hull joined → Outfitting → Launched → Sea trials → Delivered. Only dated milestones listed below are independently recorded as milestone events.
Recorded dated milestones
  • 25 July 2024 — Hull and superstructure joined
  • 25 July 2024 — Outfitting started
Latest recorded progress

Project 410's aluminium hull has been turned upright. Royal Huisman is progressing onboard systems, outfitting and the remaining structural work.

Latest verified update
25 July 2024
Dated milestones
2
Source records
2
Record verification: Source-backed · Data confidence: High
Interpretation: A recorded stage, expected year, expected date or delivery statement reflects the latest information held in the Superyacht Guide record. A passed expected date without an actual milestone should trigger re-verification; it should not automatically be described as an official delay. Builder pipeline counts represent only public project records in this database.